We're building a chapel & need your help!

Our facility houses up to 70 men & we struggle to hold chapel, worship, & meetings in our kitchen/dining area. Please consider giving of your time, skills, or money to help us complete this project. Call (601) 213-8536 for more information on volunteering or follow this link to give: https://mercyhousetc.breezechms.com/give/online (Please select Chapel Fund from drop-down)

thermometer-poster-phase-III

PHASE I

Costs: $57,500

Concrete: $23,000

Plumbing Rough In: $5,000

Forming Labor: $5,800

Concrete Form Materials: $5,700

Dirt Work & Pad: $18,000

PHASE II

Costs: $66,000

Roofing Installation: $15,000

Framing Labor: $15,000

Framing Package: $36,000

PHASE III

Costs: $40,700

Sheetrock: $12,000

Wood Trim: $6,700

Insulation: $6,500

Plumbing Installation: $3,500

Electrical Installation: $12,000

PHASE IV

Costs: $76,000

Sound Equipment: $18,000

Flooring: $18,000

Painting: $16,000

Sewage System: $5,000

HVAC: $15,000

Total Goal Cost

Project Total: $228,200